It has been a brave few days since dissertation hand in. Now, I am set to be back on track with creating my graduation film.
Here is an extract (I took out the 'notes' column for here) from the production schedule I submitted in my pre-production portfolio:
Month
|
Week
|
Task
|
January
|
||
6th-10th
|
Puppet Making
|
|
13th-17th
|
Puppet Making
|
|
20th-24th
|
Set Making
|
|
27th-31st
|
Set Making & Rigging
|
|
February
|
3rd-7th
|
Animating: Opening hospital scene
|
10th-14th
|
Animating: Parent-doctor-machine scene
|
|
17th-21st
|
Animating: Closing scene
|
|
24th-28th
|
Animating: Clean-up/retakes
|
|
March
|
3rd-7th
|
Animating: Swing scene
|
10th-14th
|
Animating: Skipping rocks scene
|
|
17th-21st
|
Animating: House scene one: afraid
|
|
24th-28th
|
Animating: House scene two: unafraid
|
|
31st-4th
|
Animating: Overruns & Retakes
|
|
April
|
7th-11th
|
Post: Special effects
|
14th-18th
|
Post: Special effects & Sound design
|
|
21st-25th
|
Post: Special effects & Sound design
|
|
28th-2nd
|
Post: Audio edit & Video assembly
|
|
May
|
5th-9th
|
Final Mix
|
12th-16th
|
Delivery
|
As you can see, I'm set to be extremely busy. However,I'll try to post progress updates as often as I can!